Date
Activity
September 5, 2013 clear250.gif
Advisory Board convened
September 5 - 10, 2013
Wiki Orientations for Advisory Board As Needed
September 5 - 10, 2013
Advisory Board reviews/adds to Press Clippings
September 11 - 29, 2013
Advisory Board answers the Research Questions
September 30 - October 6, 2013
Advisory Board makes first pass at Rankings
October 7 - October 18, 2013
NMC Staff write the Report
October 19, 2013
Report in layout and design
October 21, 2013
Final Draft of the Report sent to Advisory Board
October 22, 2013
Preview released at National ICT Conference in Oslo, Norway

The three most critical periods for Advisory Board members are September 11 - 29, when the data are collected, then September 30 - October 6, when the rankings are produced. These dates are highlighted in red.